2026
January 2026 – Village awarded additional $1.5 million in STP funding
2025
June 2025 – Village awarded $3.0 million in ITEP funding
2024
December 2024 – Right-of-way acquisition begins
2022
June 2022 – Phase II Engineering begins
December 2022 – Village awarded $7.0 million in federal discretionary funds
April 2022 - Please join us for the Public Open House being held April 28, 2022.
February 4, 2022 – RMK Virtual Public Event & Traffic Flow Model
2020
October 30, 2020 – Village applies for Illinois Transportation Enhancement Program (ITEP) funding for bike path & roadway lighting portions of the project
October 15, 2020 – Village awarded $3.5 million in STP funding
March 16, 2020 – Village applies for Surface Transportation Program (STP) funding for Phase II Design Engineering, Right-of-Way Acquisition and Construction
2019
December 10, 2019 – Presentation to Village Board on Alternatives Evaluation
2018
December 3, 2018 – Public Open House
April 17, 2018 – Phase I Preliminary Engineering contract awarded to Patrick Engineering